Costs continue to climb for Hall Street pier

Inflation and supply chain issues are just some of the reasons that Nelson’s Hall Street pier project will cost more than $4 million, which is more than a million dollars over the original $2.6 million budget.

 When the project was proposed back in 2020 the cost was quoted at $2.6 million was later increased to $3.5 million and now is estimated to cost $4.4 million.

 “Increased costs have forced us to look at how we can reduce site costs,” says public works director Colin Innes. “These increases, and issues, are going to push phase one’s completion date from December to the end of January.”

Innes says construction concerns they didn’t plan for have started coming forward.

“We got hit with the issues about pilings and the condition of the subsurface in the lakebed,” Innes says. “This has resulted in having to drive deeper piles and of course more welding is required to provide more support.”

He says with all the additional work the team has to find additional ways to save money while still keeping the aesthetics and scope of the project the same.

“We recognize that we need to find savings because costs are being driven up,” he says. “One way was to look at redesigning the canopy itself for the pier.”

Innes says the designers are looking at a few alternative plans to save more than a million dollars.

“The designers came up with the idea of shortening the pier,” he says. “Also, creating the swim platform at the end of the pier will bring the cost down.”

To remain on budget the city will need to trim another million off the budget.

Innes says the canopy portion might have to be scrapped for the year if the city cannot contain costs for the project or find a new grant to cover it.

He says they project the pier will be $185,000 over budget, but the team is working to address cost pressures.

City council approved construction on April 19 with a construction budget of $3.5 million. Funding came from a contribution of $2 million from the city, $500 thousand from Columbia Basin Trust and a federal grant of $1 million.

The pier will replace the structure which was built back in 1986 and will include a new Ladybird display building that was scheduled to be completed in December, but will be delayed until the end of January 2023.  

Continue Reading

chnv Now playing play

ckkc Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Nelson Leafs coach prepares for puck drop

Nelson Leads head coach Barry Wolff is eager for the puck to drop tonight as the KIJHL season officially begins, with Nelson hosting the Kimberley Dynamiters.

RDCK signs three-year contract with CUPE staff

The deal with Locals 748 and 2264 is retroactive to March 1, 2024 and runs until Feb. 28, 2027.

Slash scotch broom, earn cash

Landowners and residents in the Regional District of Central Kootenay are being asked to help tackle invasive Scotch broom - and get paid for their efforts.

Area restriction lifted for wildfire east of Ymir

The BC Wildfire Service has cancelled an order restricting public access to the area around the Cultus wildfire.

Premier Eby calls for “basic fairness” for B.C. ferry users during Ottawa trip

Premier David Eby said he had “productive” meetings with Prime Minister Mark Carney and several senior officials during his two-day trip to Ottawa.
- Advertisement -