The Nelson Civic Theatre Society (NCTS) has been granted access the remaining $750,000 of a city line of credit to help keep its redevelopment project moving.
Nelson city council approved the society’s request at a special council meeting on Nov. 13, allowing it to draw on the remaining balance of a $1-million line of credit originally approved in 2019.
According to a staff report, the funding is needed to cover outstanding construction costs, including a September invoice. Paying those costs will allow eligible expenses to be submitted for reimbursement through the federal Investing in Canada Infrastructure Program.
That reimbursement is then expected to help cover the society’s October construction invoice.
Chief Financial Officer Chris Jury told council the theatre redevelopment project is now about 52 per cent complete.
“This funding is required in order for them to have the cash flow to pay these immediate invoices,” said Jury.
The city had previously authorized $250,000 in advances under the line of credit. With the latest approval, the society can now access the remaining $750,000, bringing the total available advances to the full $1 million.
That means the city could have its entire line of credit advanced to the society while the redevelopment is still only about halfway complete.
The project will see the historic single-screen theatre converted into a three-screen cinema. However, the society has previously warned it is facing a significant financial shortfall while the theatre remains closed.
Earlier this month, the society put out a public call for donations, setting a $100,000 fundraising goal by the end of the year.
The staff report acknowledges some financial risk to the city if fundraising, grant reimbursements or the society’s future operations do not proceed as forecast.
However, staff said that risk is mitigated through requirements for supporting financial documentation with each disbursement, along with frequent progress meetings and updates from the society.
The report also notes the timing and amount of repayment will depend on grant recoveries, fundraising and the society’s future operating capacity.
The city will continue reviewing supporting financial documentation and monitoring the amount owing under the line of credit.
The redevelopment project is estimated to cost $7.4 million.